25.11.2021

Taylors Run Construction Update November 2021

2021 has been a stellar year not only for Taylors Run, but for the whole North-West corridor. With stage 6 having just been released ahead of schedule due to an overwhelming demand for vacant land, we are excited to share our latest construction update at Taylors Run.

Sewer and drainage works are complete in Stage 1, with stages 2 and 3 nearing completion.

Stage 1 road excavation and installation of the road base has just been completed and the watermain is now being installed.

Stage 4 topsoil stripping and earthworks are currently underway with sewer works to commence in the coming weeks.

With all of the above in place, titles are on track for stage 1 in Q2 2022 and stages 2, 3 and 4 in Q3 2022. 

It’s been a rocky start with lockdowns and construction shutdowns but Wolfdene and Blueways are extremely proud of the work being done by our sales staff and all of the civil workers. They have been keeping everything operational onsite so our clients can move into their new homes as soon as possible. 

 

Images captured from drone footage of Taylors Run in October 2021